Bruce Highway - Sarina to Cairns - Overtaking Lanes

A A A

Funding Programme:Investment Road and Rail Programme
Status:Under construction
Transport Mode:Road
Expected Start/Finish:June 2011 - Mid 2017
Estimated Project Cost:$67,800,000
Australian Government Contribution:$67,800,000
Local Council/Shire:Burdekin Shire Council,Hinchinbrook Shire Council,Townsville City Council,Cairns Regional Council,Cassowary Coast Regional Council,Mackay Regional Council,Whitsunday Regional Council
State:QLD
Corridor:Brisbane - Cairns

Project Description

The project involves the construction of up to 30 new overtaking lanes between Sarina and Cairns.

Benefits

The works will improve safety and reduce travel times on the Bruce Highway.

Funding

The Australian Government is providing $67.8 million to the project.

Timetable

Construction commenced on the first of the overtaking lane projects in June 2011 and works are expected to be completed in mid 2017.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 16/12/2016