Echo Hills Road, Mulla Creek (Rural Road) - 042284-10NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jun 2012 - Sep 2013
Australian Government Contribution:$166,842
Local Council/Shire:Tamworth Regional Council
State:NSW

Project Description

Timber bridge was washed away in flooding event in 2008. Temporary replacement bridge was installed in 2009 but is on a lower level and is repeatedly washed away in minor flooding events, cutting off public road access to residents of Echo Hills Road east of the bridge.

Replace temporary bridge structure with permanent concrete bridge at a higher level and on an improved alignment. Works include construction of bridge approaches and concrete bridge.

Total cost of proposed project is $279,643

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2013