Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jan 2013 - Feb 2014 |
Australian Government Contribution: | $595,713 |
Local Council/Shire: | Wellington Shire Council |
State: | VIC |
Project DescriptionExisting 4.5m wide road - with the increasing traffic volumes, edges of seal are constanting breaking away and gravel shoulders have increasing numbers of potholes.
Rehabilitate and widen the 4.5km section of road to 6.0m including additional pavement. Widening, shoulder reconstruction, drainage and signage works are required. Bituminous sealing - 7mm primerseal. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/05/2014