Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2012 - Mar 2014
Australian Government Contribution:$160,026
Local Council/Shire:Glen Innes Severn Council
State:NSW

Project Description

Gravel road shoulders erode quickly due to relatively steep slope (average longitudinal gradient of nearly 5%) and vehicle movements on parking lanes, leading to frequent road maintenance to meet service levels.

Construct concrete edge restraints on each side of Oliver Street to support and delineate the road pavement, and widen the pavement including bitumen sealing the two parking lanes on each side of the existing sealed carriageway.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2014