Konagaderra Road - 046605-12VIC-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2012 - Apr 2014
Australian Government Contribution:$1,435,439
Local Council/Shire:Hume City Council
State:VIC

Project Description

Safety problems - This section of the road has a very narrow pavement (approx 4m) and poor shoulders, with a 100kph speed limit. This is a major north-south road link through the northern part of the municipality.

Widen the pavement to approx 7m and provide constructed shoulders.

Total cost of proposed project is $1,850,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.