Bath Street - 047526-12NT-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2013 - Oct 2013
Australian Government Contribution:$200,000
Local Council/Shire:Alice Springs Town Council
State:NT

Project Description

Bitumen surface is cracked and failed due to increased traffic volumes and road openings

It is proposed to remove the existing bitumen surface and sub base, raise existing power and water infrastructure and reconstruct and reseal the road.

Total cost of proposed project is $300,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.