Jump to Content

Main Street, Balgowan - 048275-12SA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2013 - Dec 2013
Australian Government Contribution:$90,220
Local Council/Shire:District Council of Yorke Peninsula
State:SA

Project Description

Current road construction not allowing adequate stormwater drainage resulting in seal breaking down. Unsealed onroad parking corrugated and pitted at seal edge and stormwater pooling is common.

reseal of road length from the corner of Fifth Street to the the corner of Balgowan Road, including construction of footpath and kerbing and sealing of onroad parking area

Total cost of proposed project is $119,260

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2014