Thompson Street, Moree - 048312-12NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Feb 2013 - Jul 2013
Australian Government Contribution:$142,376
State:NSW

Project Description

Poor drainage caused by damaged kerb and gutter. Cracking and rutting of pavement.

Full reconstruction of road surface and replacement of kerb and gutter.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/03/2014