Kirrama Range Road

A A A

Funding Programme:Investment Road and Rail Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:December 2013 - December 2014
Estimated Project Cost:$4,766,000
Australian Government Contribution:$1,000,000
Local Council/Shire:Cassowary Coast Regional Council
State:QLD

Project Description

The project involved an upgrade of the Kirrama Range Road including the replacement of ten bridges, drainage works and road reconstruction.

Benefits

The project enabled the opening of the road to benefit tourism, traditional owners and local cattle station owners.

Funding

The Australian Government provided $1 million to the project, in partnership with the Queensland Government and the Cassowary Coast Regional Council.

Timetable

Construction commenced in December 2013 and was completed in December 2014.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 12/02/2015