Jump to Content

Dwyers Creek Road, Moruya - 049227-13NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2013 - Dec 2013
Australian Government Contribution:$362,400
Local Council/Shire:Eurobodalla Shire Council
State:NSW

Project Description

Narrow gravel road showing significant loss of pavement due to increased traffic

Works will include approximately 400 metres of reconstruction and 600 metres of two coat seal to improve safety. Typical cross section is a 7.2 metre wide bitumen seal on a 9.2 metre wide pavement

Total cost of proposed project is $453,233

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/04/2014