Jump to Content

North Street, Devonport - 049264-13TAS-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jan 2014 - Mar 2014
Australian Government Contribution:$99,077
Local Council/Shire:Devonport City Council
State:TAS

Project Description

Existing wearing surface and pavement failed over the full width of the road, poor amenity and hazard for road users. On bus route for last 10 years which has resulted in greater loadings on pavement and accelerated failure. Moreover, a lack of adequate subsoil drainage combined with road surface level being natural surface has likely resulted in water ingress and pavement failure.

Full pavement box-out (length of approx 90m), associated with sub-soil drainage install behind kerb and channel on both sides of road. Replace section of kerb and channel, upgarde stormwater pits and driveway crossover if required.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/04/2014