Jump to Content

Hampton Road - 049624-13NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Nov 2013 - Nov 2013
Australian Government Contribution:$150,000
Local Council/Shire:City of Lithgow Council
State:NSW

Project Description

Road is badly potholed, patched and has lost shape. Correction/total rehabilitation of road pavement including removal of thick timbers shadowing road to allow more sunlight onto pavement and assist user safety.

Road will be reconstructed with new road base material and reshaped with appropriate cross-fall. Works will also include the upgrade/install additional drainage culverts. Application of new 2-coat bitumen seal surface. General line marking, sign/guide posts and reflective pavement markers to assist night user safety.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2014