Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Aug 2013 - May 2014
Australian Government Contribution:$220,000
Local Council/Shire:Gympie Regional Council
State:QLD

Project Description

The existing road surface has deteriorated due to high traffic volume.

Apply a 40mm asphalt overlay to existing road seal

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.