Inkerman Street, St Kilda, - 049953-13VIC-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2013 - Sep 2013
Australian Government Contribution:$93,002
Local Council/Shire:City of Port Phillip
State:VIC

Project Description

Deformed asphalt surface has been identified through road inspections. The Pavement surface has changed from the originally constructed profile, which may directly influence the riding quality, water ponding and skid resistance. Asphalt resheeting improves pavement performance with regards to the strength and riding quality.

30mm minimum (approx 40mm)depth asphalt overlay of the existing surface along 175m length and 14m wide (area=2,450m2)

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2014