Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Dec 2013 - Mar 2014
Australian Government Contribution:$150,000
Local Council/Shire:Moreton Bay Regional Council
State:QLD

Project Description

Existing road is in poor condition ( cracked, rutted and rough ) and requires rehabilitation to cater for traffic flows from the freeway, school and shopping centre.

Rehabilitation of the existing pavement for a distance of approximatly 260 metres.

Total cost of proposed project is $484,749

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.