Jump to Content

Brazier Road - 050390-13WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2013 - Jan 2014
Australian Government Contribution:$1,007,928
Local Council/Shire:City of Wanneroo
State:WA

Project Description

Substandard intersection layout at Brazier Road/Wilkie Avenue, substabndard existing road carriageway (Brazier Road), limited stormwater control and, poor cycling and pedestrian accessibility to the local beach (ie: the Yanchep Lagoon).

Installation of a roundabout at the intersection of Brazier Road with Wilkie Avenue, rehabiliation of the existing Brazier Road carriageway west of its intersection with Wilkie Avenue, limestone mass block retaining wall on relaigned section inclusive of new carriagway, stormwater network inclusive of an underground storage/inflitration system, pathways and a temporay cul-de-sac head opposite the Yanchep Kiosk. NB: Stage 2 is separately budgetted and is scheduled in the City's 10-Year Capital Works Program for construction in the 2014/2015 finacial year.

Total cost of proposed project is $2,454,259

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/03/2014