Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Apr 2014 - May 2014
Australian Government Contribution:$217,450
Local Council/Shire:Campaspe Shire Council
State:VIC

Project Description

Rehabilitation of the existing pavement as it has reached intervention level, it is described as being in very poor condition with serviceability now being affected and increased maintenance costs.

Urban pavement rehabilitation including: o Rip existing pavement o Apply crushed rock to create pavement formation o Stabilise and prepare the pavement where required o Primer Seal or Asphalt application (Asphalt 70mm depth for 200m and 7m/14mm rubber Seal for 131m application) o Reinstate line marking effected by the works, as required to Australian Standard guidelines o Replace / renew guide posts o Kerb and channel to be reinstated o Site clean-up.

Total cost of proposed project is $252,707

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2014