Hare Street, Echuca - 050496-13VIC-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Apr 2014 - May 2014
Australian Government Contribution:$110,846
Local Council/Shire:Campaspe Shire Council
State:VIC

Project Description

Rehabilitation of the existing kerb and channel as it has reached intervention level, it is described as being in very poor condition with serviceability now being affected and increased maintenance costs.

Replacement of a 440m section of kerb and channel. This section has been identified as requiring renewal based on condition and prioritised based on condition assessments.

Total cost of proposed project is $170,565

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.