Newmans Creek Road Koonya - 050642-13TAS-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2013 - Sep 2013
Australian Government Contribution:$19,560
Local Council/Shire:Tasman Council
State:TAS

Project Description

The existing Timber bridge deck needs to be replaced as it is susceptible to collapes due to the heavy trucks and machinery that go over it to the quarry further up Newmans Creek Road.

Timber deck to be replaced with a concrete deck, rock stabilisation to be undertaken on the approach and departure and armco railing to be installed.

Total cost of proposed project is $37,624

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2013