North West Coastal Highway - Minilya to Barradale Upgrade and New Bridges Between Barradale and Nanutarra

A A A

Funding Programme:Investment Road and Rail Programme
Status:Under construction
Transport Mode:Road
Expected Start/Finish:January 2015 - October 2016
Estimated Project Cost:$126,680,000
Australian Government Contribution:$100,720,000
Local Council/Shire:Shire of Ashburton,Shire of Carnarvon
State:WA

Project Description

The project will widen and strengthen the North West Coastal Highway between Minilya and Barradale, and construct two bridges over low-level floodway crossings between Barradale and Nanutarra.

Benefits

The project will improve service reliability and reduce road closures on the highway. It will improve freight access and reduce freight costs to significant new resource operations in the eastern Pilbara and northern Gascoyne regions, and their supporting towns.

Funding

The Australian Government is contributing $100.7 million towards the $126.68 million project.

Timetable

Construction on Stage 2 (Mia Mia to Barradale and Bridges at Cave Creek and Goodeman Creek, between Barradale and Nanutarra) commenced in March 2015.  The bridge works commenced on 30 May 2015.  Section 2 is expected to be completed by October 2016.  This marks completion of the full project.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/10/2016