Jump to Content

Weipa to Mapoon Road ( Rural Road) - 051568-13QLD-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:May 2014 - Jun 2014
Australian Government Contribution:$59,849
Local Council/Shire:Mapoon Aboriginal Council
State:QLD

Project Description

Existing culvert capacity at this location is inadequate and the road overtops in heavy rain events

Add 2x 1200x450 culvert barrels at the location of the existing single barrel culvert and provide a gravel overlay over the completed culvert

Total cost of proposed project is $1,900,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2014