Department of Infrastructure and Regional Development print logo Building our Future print logo

Donohue Highway (Rural Road) - 051572-13QLD-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2014 - May 2014
Australian Government Contribution:$55,976
Local Council/Shire:Boulia Shire Council
State:QLD

Project Description

This section has been damaged by Road Trains bringing cattle from the Northern Territory to Queensland for sale because of the prevailing drought conditions. Sections have turned to bulldust because of the lack of rain to compact the road. Other sections have been rutted. This has resulted in dangerous road conditions.

It is proposed to water, grade & roll the road to bring it to an acceptable level. The total project cost is $255,000 including $127,500 of TIDS funding. R2R funding will be $55,976 & Council will contribute the balance of $71,524.

Total cost of proposed project is $310,889

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2014