Midland Highway Safety Works Package – South of Spring Hill

A A A

Funding Programme:Investment Road and Rail Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:10 December 2014 - 24 July 2015
Estimated Project Cost:$5,825,000
Australian Government Contribution:$4,660,000
Local Council/Shire:Southern Midlands Council
State:TAS
Corridor:Hobart - Burnie

Project Description

The project widened shoulders and installed wire rope barriers on the Midland Highway south of Spring Hill.

Benefits

The project achieved a 3 Star AusRAP Safety Rating on this section of the Midland Highway. The project improved safety, capacity and overtaking opportunities.

Funding

The cost of the project was $5,825,000. The Australian Government contributed $4,660,000 and the Tasmanian Government $1,165,000.

Timetable

Construction commenced on 10 December 2014 and was completed on 24 July 2015.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 20/07/2016