Winnejup Road (Rural Road) - 051890-14WA-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Feb 2015 - Apr 2015
Australian Government Contribution:$85,756
Local Council/Shire:Shire of Bridgetown Greenbushes
State:WA

Project Description

This road is narrow and has failed badly. It requires reconstruction to a to a wider standard to improve road safety and to cater for increasing regional traffic movements.

Remove vegetation as required to widen formation to a 9.0 metres, upgrade/extend drainage crossings, construct gravel pavement and spray seal to 7.0 metres.

Total cost of proposed project is $215,756

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2015