Larrys Mountain Road, Moruya - 051975-14NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Oct 2014 - Dec 2014
Australian Government Contribution:$40,000
Local Council/Shire:Eurobodalla Shire Council
State:NSW

Project Description

Narrow gravel road showing significant loss of pavement

Works proposed comprises of breaking up and loosening the existing road surface, placement and compaction of new gravel, minor widening to 7.5 metres, minor clearing and re-establishment of table drains some 7500 square metres

Total cost of proposed project is $46,609

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.