Jump to Content

Richardson Street - 052109-14NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Nov 2014 - Jan 2015
Australian Government Contribution:$296,734
Local Council/Shire:Fairfield City Council
State:NSW

Project Description

The road section is affected by numerous crocodile shaped cracks, failures of road base course and deformation of road surface, which makes it very rough with poor ride quality

The proposed work include the rehabilitation of road base by cement stabilisation, placement of spray seal and resurfacing with hot mix asphalt. Length = 432m, Width = 8.6 m, Area =3715m2

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/09/2015