Davies Avenue,Vaucluse - 052277-14NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Dec 2014 - Jan 2015
Australian Government Contribution:$122,942
State:NSW

Project Description

Road pavement is aged and upto 80% is cracked.

It is proposed to excavate the old pavement, regrade and reconstruct including kerb and gutter.

Total cost of proposed project is $182,713

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.