East Avenue, Black Forest - 052491-14SA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2014 - Jun 2015
Australian Government Contribution:$200,000
Local Council/Shire:South Australian Local Government Grants Commission
State:SA

Project Description

The road has reached the end of its useful life, suffering from texture failure, potholing and cracking. The road is also suffering from kerb and water table failure, which has also reduced the useful life of the pavement.

The proposed work includes a full road profiling over the 700 metres of road, plus replacement of kerb and gutter on both sides of the road. The road surface will be replaced with 40 millimetre thick hotmix.

Total cost of proposed project is $450,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2015