Department of Infrastructure and Regional Development print logo Building our Future print logo

Lanhams Road - 052543-14NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2015 - Oct 2015
Australian Government Contribution:$173,985
Local Council/Shire:Parramatta City Council
State:NSW

Project Description

The road surface is old and brittle. It has been affected by cracks and potholes, which makes it very rough to drive on. The disintegration of asphalt at road edges has also occured. Some sections of kerbs have been damaged and displaced.

The proposed work will include repair of failed pavement areas and resurfacing of the road with asphalt. Damaged or displaced sections of kerbs and gutters will be repaired before resurfacing. Length = 213 m; Width = 12 m; Area = 2556 m2.

Total cost of proposed project is $276,377

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/07/2016