Department of Infrastructure and Regional Development print logo Building our Future print logo

Wonwondah Toolondo Road Bridge over Norton Creek, (rural bridge), Horsham 3400 - 052888-14VIC-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jan 2014 - Nov 2015
Australian Government Contribution:$178,344
Local Council/Shire:Horsham Rural City Council
State:VIC

Project Description

Severe cracking in the bridge as a result of which the load capacity was reduced down to 5 tonne limit.

Replacement of existing bridge with crown units wide enough (8.8m) to accommodate wider trucks. Length 30 metres.

Total cost of proposed project is $400,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2016