Department of Infrastructure and Regional Development print logo Building our Future print logo

Martin Street, Ballina - 053005-14NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2014 - Sep 2014
Australian Government Contribution:$104,800
Local Council/Shire:Ballina Shire Council
State:NSW

Project Description

Old pavement and seal has failed showing pavement rutting and shoving with significant patching, which requires high maintenance resources.

Reconstruction of pavement and seal for length of approximately 200 metres with width of 8-10 metres including excavation and replacement of unsuitable subgrade and reconstruction of Skinner Street intersection.

Total cost of proposed project is $252,641

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2014