Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Nov 2014 - Mar 2015
Australian Government Contribution:$266,165
Local Council/Shire:Derwent Valley Council
State:TAS

Project Description

Stormwater flooding due to inadequate drainage causing damage to kerb and channel and footpath. This has resulted in dangerous situation for pedestrians, residents and drivers due to water escaping and running across the road.

New 375 diameter stormwater pipe of 170 metres, 560 metres of kerb and channel, new grated side entry pits quantity 8,plus pavement stabilisation and sealing.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2015