Bowan Park Road, Lidster - 053269-14NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Aug 2014 - Feb 2015
Australian Government Contribution:$154,897
Local Council/Shire:Cabonne Shire Council
State:NSW

Project Description

Badly scoured and areas of nil drainage. Pavement failures and width currently 5m to 5.5m wide. Overhanging limbs and dangerous overhanging trees.

Redefining drainage with excavation and grader. Widening and stabilising to a 8m formation and 7m seal for 970m. Vegetation including tree removal and branch removal to improve sight distance in the road corridor.

Total cost of proposed project is $305,531

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2015