Stuart Street - Innamincka Township - 053302-14SA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jan 2016 - Dec 2016
Australian Government Contribution:$118,116
State:SA

Project Description

The existing road is unsealed and become dusty and corrugated in the summer and slippery after rain events. Dusts generated by traffic linger within the town, causing safety and health issues to the local road users and local residents.

The work will involve reconstructing and sealing of the entire length of Stuart Street. Stuart Street is 340 metres long by 7 metres wide. The work will mitigate the dust problem and improve accessibility to properties for local residents.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2017