Northern Territory Roads Productivity Package

A A A

Funding Programme:Investment Road and Rail Programme
Status:Under construction
Transport Mode:Road
Expected Start/Finish:2014 - 2018
Estimated Project Cost:$106,000,000
Australian Government Contribution:$90,000,000
State:NT

Project Description

The package of works consists of six projects on the Northern Territory regional roads network, as follows:

  • Roper Highway: Bridges over Roper and Wilton Crossing ($40 million);
  • Port Keats Road: Improve Flood Immunity at the Moyle River Floodplain plus road realignment in some sections ($20 million);
  • Arnhem Link Road: Upgrading sections of Arnhem Link Road ($11 million);
  • Buntine Highway: Pavement Strengthening and Widening ($10 million);
  • Central Arnhem Road: Bridge over Rocky Bottom Creek ($15 million);
  • Santa Teresa Road: Upgrading sections of Santa Teresa Road ($10 million).

Funding

The Australian Government has committed $90 million to the Package, with the Northern Territory Government to contribute $16 million.

Timetable

Construction commenced on the first of the projects in 2014, with the full programme to be completed by 2018.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.