Banksia Street, Kununurra town site - 053464-14WA-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2014 - Apr 2015
Australian Government Contribution:$70,695
Local Council/Shire:Shire of Wyndham East Kimberley
State:WA

Project Description

Existing wearing course comprising sprayed bitumen chip seal has reached end of its serviceable life

Scarify top 3mm-5mm sealed road pavement surface and supply and lay 30mm average compacted thickness 10mm hot mix asphalt Reinstate line marking of on-street car parking bays following completion of asphalt overlay

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2015