Oval Place (Nyngan) - 053957-14NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2015 - Apr 2015
Australian Government Contribution:$48,557
Local Council/Shire:Bogan Shire Council
State:NSW

Project Description

Existing formed only section of street is not centered on the road reserve and is partly impassible in the wet and creates a dust problem for residences when dry.

Reconstruct 270 metres of formation on the correct alignment, provide a 200mm thick crushed rock pavement and 14mm bitumen seal.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2017