East Parade, Buxton - 053978-14NSW-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:Sep 2014 - Nov 2014
Australian Government Contribution:$125,092
Local Council/Shire:Wingecarribee Shire Council

Project Description

The road has been previously resheeted with recycled concrete base containing asbetos contamination

Construction and sealing of the road to encapsulate the existing contamination as per approved Asbestos Management plan incuding table drain renewel

Total cost of proposed project is $166,230

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/04/2016