Kendall Street, Wodonga, Victoria, 3690 - 054141-14VIC-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2015 - Apr 2015
Australian Government Contribution:$215,000
Local Council/Shire:Wodonga City Council
State:VIC

Project Description

Road pavement shows significant areas of failure, including shoving, cracking and potholing. Kerb and channel has displaced and holds water in some places. High maintenance costs associated with ongoing inspection and repair. Road safety associated with potholed and shoved pavement.

Stage 1 (Chapple Street to Kane Road) – Full road reconstruction, including removal and replacement to 400mm depth of 3000 sqm of existing failed pavement, subgrade replacement as required, removal and replacement of approximately 135 m of kerb and channel. Install new storm water drains and inlet pits. Prepare and place initial 7mm stone seal and 40mm hotmix final seal. Stage 2 (Kane road to end of seal) - Part road reconstruction including removal and replacement to 300mm depth of 700 sqm of existing failed pavement, prepare and place initial 10mm stone seal. Supply and place 40mm hotmix final seal over full area (2100sqm)

Total cost of proposed project is $466,436

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.