Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2015 - Jun 2015
Australian Government Contribution:$215,000
Local Council/Shire:Wodonga City Council
State:VIC

Project Description

Road pavement shows significant areas of failure, including shoving, cracking and potholing. Kerb and channel has displaced and holds water in some places. High maintenance costs associated with ongoing inspection and repair. Road safety associated with potholed and shoved pavement.

Road reconstruction, including removal and replacement to 300mm depth of 5100 sqm of existing failed pavement, subgrade replacement as required, removal and replacement of approximately 420 m of kerb and channel, remove and replace associated concrete driveway and footpath pavement to match new kerb where required. Reconnect house drain connections and reset storm water inlet pits to match new kerb. Install new storm water drains and inlet pits. Prepare and place initial 7mm stone seal and 40mm hotmix final seal. Repaint line marking.

Total cost of proposed project is $425,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2015