Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Tilden Drive - 054708-14WA-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Feb 2016 - May 2016
Australian Government Contribution:$155,650
Local Council/Shire:City of Swan
State:WA

Project Description

Deterioration of parts of the timber sub structure. Some timber elements are considered to be below standard in terms of strength. The guardrail is also below standard. The existing timber deck does not have adequate load rating. ** WA Special Bridge Project **

Some timber sections to be replaced by steel beams , some timber sections will be steel Reinforced. The bridge deck will have a reinforced concrete overlay and new steel guardrail will be installed. The proposed construction dates are estimates at this stage. Works are to be conducted by Main Roads WA. This project will also be funded by the WALGGC and Main Roads WA.

Total cost of proposed project is $250,285

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/10/2017