Gooding (Rd Rural Road) - 054763-14WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2014 - Oct 2014
Australian Government Contribution:$50,000
Local Council/Shire:Shire of Dumbleyung
State:WA

Project Description

Lack of gravel causing slippery surface during wet conditions and rutting during dry periods

Clear, reform, upgrade drainage, widen and resheet with gravel to 8 metre surface

Total cost of proposed project is $114,465

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.