Eric Street, Bundeena - 055074-14NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:May 2015 - Jul 2015
Australian Government Contribution:$156,148
Local Council/Shire:Sutherland Shire Council
State:NSW

Project Description

Significant pavement failure. Surface cracking, potholes due to pavement base and sub-base failure. Road pavement has exceeded its service life and is need of renewal.

Road pavement rehabilitation works for the area of 5321 sqm. Works include stabilise the pavement base using cement( 200mm thick base layer) and application of two coat bitumen seal using 14mm/10mm aggregates.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.