Church Terrace, Walkerville - 055208-14SA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Dec 2014 - May 2015
Australian Government Contribution:$54,286
Local Council/Shire:Corporation of the Town of Walkerville
State:SA

Project Description

Seal has reached the end of its useful life and needed to be profiled and resealed. In order to do this kerb and gutter repairs were needed before the road could be resealed.

Identified kerb being removed and replaced to ensure sufficant drainage and also a straightline for the road reseal. Upon completion of kerbing works the road to be profiled to remove severity of gradient before the entire seciton of road be resealed.

Total cost of proposed project is $118,808

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/10/2015