Wonnerup South Road (Rural Road) - 055228-14WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Dec 2015 - Mar 2016
Australian Government Contribution:$30,375
State:WA

Project Description

The two year old primer seal was laid following widening and reconstruction in 2014. A second seal is now essential to provide a long lasting surface that will significantly extend the life of the road.

A second coat spray seal will be applied to the road surface to protect the roads basecourse and extend the longevity of the road as per the Citys Road Asset Management Plan

Total cost of proposed project is $30,397

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.