Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Aug 2015 - Nov 2015 |
Australian Government Contribution: | $103,273 |
Local Council/Shire: | Campbelltown City Council |
State: | NSW |
Project DescriptionThe road surfacing is affected with moderate levels of ravelling and crocodile cracking
The proposed treatment includes rectification of the asphalt fatigue area with heavy patching treatment first. Then the whole section will be treated with hot mix asphalt with interlayer seal. Length is 435m and average width is 10.3m. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/12/2015