Segenhoe Street, Aberdeen - 055664-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:May 2016 - Dec 2016
Australian Government Contribution:$770,366
Local Council/Shire:Upper Hunter Shire Council
State:NSW

Project Description

Narrow failed pavement, poor drainage.

Install 30m x 375 dia. RCP at the intersection of Segenhoe and Perth Streets and construct two kerb inlet pits. Renew 20 metres of 450x300 box culvert at Segenhoe and St Heliers Street intersection. Construct 700 metres of new kerb and gutter to design levels (along the eastern side of Segenhoe St from Perth to St Heliers Street).Rehabilitate 5000m2 pavements (construct new pavement from kerb to existing pavement and provide 150mm gravel overlay to existing pavement).Provide two coat 14/7mm bitumen seal. Length of road to be upgraded 0.420km x 11 metres wide, total seal area 5000m2.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/07/2017