Department of Infrastructure and Regional Development print logo Building our Future print logo

Balladoran Railway Road (Rural Road) - 056047-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Oct 2015 - Oct 2015
Australian Government Contribution:$31,722
Local Council/Shire:Gilgandra Council
State:NSW

Project Description

Primary through road formed from natural sandy clay material. In wet conditions the road becomes very slippery and in dry periods the road is prone to deep rutting and pot holes.

Reshape road and gravel sheet – Win and cart gravel – Spread gravel at 6m wide X 130mm thick, compact to 100mm. Re-establish table drains and mitre drains.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2016