Mark Road East - 056105-15QLD-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:Dec 2015 - Mar 2016
Australian Government Contribution:$246,461
Local Council/Shire:Sunshine Coast Regional Council

Project Description

The proposed section has the following defects: the existing asphalt surface is oxidised, brittle and ravelled with crocodile cracking.

Asphalt Resurfacing: Profile edges to key-in with the concrete kerb and channel; Waterproofing and crack alleviation bitumen sprayed seal; 50mm thick Dense Graded Asphalt Overlay (using size 14mm nominal aggregate).

Total cost of proposed project is $250,941

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.