Jump to Content

Alamein Street, Shepparton - 056584-15VIC-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2016 - May 2016
Australian Government Contribution:$237,000
Local Council/Shire:Greater Shepparton City Council
State:VIC

Project Description

base failure/shoving /depressions inadequate drainage cracked and sunkenn kerb and channel

Replace 351m failed kerb and channel , Mill/remove 40mm depth failed sections of pavement & overlay with 10mm A10E Type HP asphalt @ 30mm 2,030m2

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/07/2016